Cycling facilities in ParisDesign and construction management

Lieu : Paris, France

Client : City of Paris

Date : 2021 - 2026

Le projet

The success of cycling in Paris, accelerated by the health crisis, has prompted City Hall to seek to perpetuate the 52 km of temporary cycling facilities (the “coronapistes”) created after the spring 2020 containment. In addition to these pre-existing facilities, 130 km of new cycle paths will be built as part of the 2021-2026 Bicycle Plan. The main aim of bicycle development projects is to create the conditions for increasing cycling use. Their priority is therefore to provide a cycling infrastructure that can address and convince people who don’t yet cycle to choose this mode.

The projects are part of the development of Parisian public spaces, which meet four general objectives:

  • Rebalance the use of public space in favor of pedestrians, bicycles, green spaces and public transport.
  • Meet the expectations of users and future users, notably through innovative approaches to involving the public in the design and implementation of the project.
  • Responding to the ecological imperative by treating spaces (summer comfort, waterproofing, source of materials, etc.) and limiting demolition.
  • Optimize work schedules and costs
52km de pistes cyclables provisoires à péréniser
130 km de pistes à construire
un plan vélo pour la période2021 - 2026

Nos missions

  • Preliminary studies (EP)
  • Pre-project studies (AVP)
  • Project studies (PRO)
  • Design approval (Visa)
  • Construction Management (DET)
  • Assistance with Acceptance Operations (AOR)
  • Organization, Control and Coordination (OPC) / Study phase
  • Organization, Control and Coordination (OPC) / Construction phase
citation

The major difficulty lies in the pace of the assignment, which is divided into several sub-projects, each costing between €1 and €5 million, for which studies have to be carried out to a (very) tight schedule, followed by preparation and supervision of the worksites. In the summer of 2022, for example, the group was working on 7 areas under study, while at the same time monitoring 5 construction sites. An organization that leaves little room for the unexpected!

Erwan Le Helloco

Project manager on the mission

Nos expertises mobilisées

Pour aller plus loin

Setec international est en charge des opérations d’aménagement dans les arrondissements suivants : 11, 12, 13, 19, 20.

Quelques unes des opérations réalisées :  Avenue Gambetta Ouest • Avenue Gambetta Est • Rue du Faubourg St-Antoine • Avenue Ledru-Rollin • Avenue d’Ivry • Avenue de Choisy • Boulevard de l’Hôpital • Avenue de Nogent • Avenue du Trône / Cours de Vincennes

citation

Découvrir d'autres réalisations

Dakar-Thies freeway


February 2003

The rapid deterioration in traffic conditions on the Cape Verde peninsula (Dakar region) in ...

Haiti Tomorrow


January 2010

Since January 2010, the Setec Group, together with Bernard Reichen Architecte Urbaniste and ...

LGV Bretagne Pays de la Loire


April 2011

The Bretagne – Pays de la Loire High-Speed Line (LGV) project is an extension of the LGV ...